A driveway crossover is the section between your property boundary and the road. It usually crosses the nature strip and sits within the road reserve, which means Central Coast Council has a say in how it’s constructed.

Council calls this a Vehicle Access Crossing (VAC).

It’s also the part of a driveway that can hold up a job if the approval, levels or inspections aren’t organised properly. This guide explains what’s involved, what to have ready and how crossover requirements affect the cost of your asphalt driveway.

Does my driveway crossover need Council approval?

Council approval is generally required when you’re constructing a new vehicle access crossing or altering an existing one. This applies whether your street has kerb and gutter or not.

Type of work Is Council approval generally required?
New driveway or resurfacing entirely inside your property boundary Usually no VAC approval
Constructing a new crossover Yes
Widening or altering an existing crossover Yes
Reconstructing an existing crossover, including changing from concrete to asphalt Yes
Changing or cutting the kerb, including a new layback Yes
Minor patch repair to an existing crossover Check with Council first

A development approval, complying development certificate or construction certificate is not the same as VAC approval. If your work involves constructing, reconstructing or modifying the crossing, you may still need separate Council approval before starting.

Requirements can depend on the type of property and proposed work, so check Central Coast Council’s current Vehicle Access Crossing information before booking a contractor.

How the Council VAC process works

The process generally involves the following steps.

1. Submit your application

Lodge the appropriate VAC application with Council, including the required drawing and application fee. Council provides guidance and a drawing template.

Some crossings require additional engineering assessment or a site-specific design. These can involve extra Council fees.

2. Wait for Council approval

Council reviews the application and determines the approved location, width, levels and other requirements for the crossing.

Read the approval carefully before arranging construction. The approved design may affect the excavation, concrete layback, asphalt work and final levels.

3. Arrange the first inspection

Before the final surface is laid, the crossing needs to be prepared for Council’s formwork or initial inspection, where required.

The crossing must be set out and ready on a suitably compacted base. Council’s application information requires inspections to be booked at least 48 hours (two business days) ahead.

4. Notify Council before construction

Council’s VAC process requires the applicant to advise Council of the commencement of work at least 7 days before work starts.

Make sure this notification is arranged before the construction date.

5. Complete the work within the required timeframe

Following a successful first inspection, Council’s application information expects the work to be completed within 14 days.

The approved plans and any conditions attached to the approval should guide the construction.

6. Arrange the final inspection

Book the final inspection at least 48 hours (two business days) ahead, as required.

Keep the approval and completion documentation with your property records. It can be useful if you sell the property or need to refer to the approved crossing later.

How long does Council approval take?

Central Coast Council’s current VAC guidance states that a straightforward application will usually be processed within 14–21 days.

If the crossing is more complex or requires a site-specific design, Council recommends allowing 28 days.

These are indicative average processing times, not guaranteed approval dates. Actual processing can vary depending on the application, site conditions and whether Council needs further information.

It’s worth allowing time for approval before committing to a construction date.

Nathan’s tips for the application

“In our experience, the application is pretty straightforward, and you can fill it all out yourself. It asks for some specific things, like a drawing and a traffic control plan.

“For the drawing, give it rough dimensions, say five by seven, and roughly sketch your driveway shape. For the traffic control plan, write that your contractor will take care of it. We do that for our jobs.”

Council’s fees and requirements can change, so check the current VAC application information and fee schedule before submitting.

What Council’s standard says about asphalt crossovers

Council’s VAC application form lists asphalt as an approved surface, with a 40mm minimum asphalt thickness.

For an asphalt crossing, Council’s standard details specify:

  • 40mm minimum asphalt on a tack coat
  • 100mm minimum compacted road base on firm subgrade

The road base needs to be properly prepared and compacted before the asphalt is placed.

What about the concrete layback?

The layback is the section of concrete that forms the dip in the kerb and allows vehicles to enter the property.

Where a layback is required, Council specifies plain concrete for this section, even if the driveway and crossover behind it are asphalt.

Council’s application form also lists plain concrete, coloured concrete and stencilled concrete as approved crossing surfaces, subject to its requirements. It does not approve pavers, tiles, exposed aggregate or stamped concrete for the vehicle access crossing.

If Council or a utility later needs to dig up the crossing, the reinstated surface may be plain concrete. Decorative finishes or asphalt may not be matched to the original surface, and the property owner may be responsible for associated costs under the applicable conditions or waiver.

Maintaining the vehicle access crossing and associated infrastructure is generally the property owner’s responsibility.

Getting the levels right

Most of the crossovers we build are inspected by Council.

“We generally get all the plans beforehand. And because we’ve been doing them for years, we’ve built a relationship with the inspectors, so things usually run pretty smoothly. Some are fussier than others. We just take our time making sure we get the levels and fall correct.”

The approved design determines the levels and gradients required at the boundary, footpath and kerb.

Getting these levels right matters for two main reasons: vehicle access and drainage.

The crossover needs to transition smoothly from the road to the driveway without creating a sharp change in grade that causes vehicles to scrape. It also needs to manage water properly, so runoff doesn’t get directed into the property or create problems for the road and footpath.

When levels are wrong, it shows.

“One of the biggest call-outs we get is cars scraping, or water running into a property.”

In Ettalong, for example, many streets have no kerb and gutter or formal drainage. A lot of the work we do there involves reducing how much water runs off the road into the property during rain or flooding.

A crossover isn’t just about laying a strip of asphalt. The levels, falls and tie-in to the existing road all need to work together.

Why crossovers cost more than the same area of driveway

Square metre for square metre, a crossover can cost more than the driveway behind it.

There are a few reasons for this.

Inspection and crew time

Council inspections can require the crew and machinery to be available at a particular time. This can mean additional time on site or waiting around between stages.

For crossover jobs, Coast Pave allows $495 including GST ($450 + GST) for inspection-related crew and plant time. This allowance covers approximately an hour and a half of crew and equipment time.

Levels and kerb tie-in

The crossover needs to meet Council’s approved levels at the kerb, footpath and property boundary.

Getting the fall right, tying into the existing kerb and keeping the gutter flowing can involve more detailed work than a straightforward driveway surface.

Traffic control

Depending on the road and the work involved, traffic control may be required. This is priced separately where applicable.

Council fees and paperwork

Council’s VAC application fee is separate from Coast Pave’s construction price.

If you’d like Coast Pave to handle the Council VAC paperwork process on your behalf, our additional charge is $495 including GST ($450 + GST).

The Council application fee is paid separately by the client. As a guide, allow approximately $500 for the VAC application through Council, but confirm the current fee before applying. Additional assessment or engineering fees may apply to non-standard crossings.

These are separate charges:

  • Coast Pave inspection and crew/plant allowance: $495 including GST
  • Optional Coast Pave Council paperwork handling: $495 including GST
  • Council VAC application fee: approximately $500, paid separately by the client

What does a crossover and driveway cost?

As a guide, a driveway and crossover of approximately 30m² in total typically costs around $5,850–$6,700 including GST (approximately $5,300–$6,100 + GST).

This guide includes our inspection allowance, but excludes Council fees, the optional Coast Pave paperwork-handling charge and any concrete layback.

Your final price depends on the size of the job, existing surface, excavation, levels, access and what needs to be removed or rebuilt.

What to have ready before you ask for quotes

Having the right information makes it easier to provide an accurate quote and avoid delays.

If possible, have the following ready:

  • Your Council approval or application number, or the drawing you’re applying with
  • Photos of the existing crossover, kerb and gutter
  • Rough measurements, including the width at the boundary, width at the kerb and length from boundary to road
  • Whether there’s a footpath to cross
  • Any pits, poles, trees or other obstacles near the proposed crossing
  • Details of any existing drainage or water pooling

We’d rather review your approval first than arrive on site and discover the approved design requires something different from what was quoted.

Common mistakes we see

Building without approval.

Unapproved work may need to be corrected to meet Council’s requirements, potentially at the owner’s cost.

Getting the levels wrong.

Poor levels can cause vehicles to scrape or direct stormwater into the property.

Booking the contractor before approval.

If approval or inspections aren’t ready, the construction date can slip.

Choosing a quote that leaves out Council requirements.

A price that doesn’t account for inspections, levels or traffic control may not be the cheapest option once the missing work is added.

Frequently asked questions

How long does a crossover take to build?

The asphalt work is usually completed in a day once the crossing is approved and the first inspection has been passed. Inspections, excavation and any concrete layback can add time.

Can Coast Pave handle the Council paperwork?

We can help you prepare the information Council needs and build to the approved plan. If you’d like us to handle the VAC paperwork process, our additional charge is $495 including GST. The Council application fee is separate and paid by the client.

Who builds the concrete layback?

A layback is concrete work and is priced separately from the asphalt. Let us know if your approval requires one, and we’ll explain how it fits into your job when we quote.

Can you build a crossover without doing the whole driveway?

Yes. We can quote crossover work on its own. Combining it with a driveway job can offer better value because some setup costs are shared.

Who looks after the crossover once it’s built?

The property owner is generally responsible for maintaining the vehicle access crossing and associated infrastructure. Check the conditions on your Council approval for the requirements that apply to your property.

Get a quote for your driveway crossover

If you’re planning a new driveway, replacing an existing crossover or connecting an asphalt driveway to the road, we can help you understand what’s involved.

Send us a few photos, rough measurements and any Council approval details you have. We’ll review the site requirements and provide a quote based on the work needed.

Contact Coast Pave Asphalt to discuss your Central Coast driveway or crossover project.